Paper
24 September 2012 Commissioning and initial performance of the Dark Energy Camera liquid nitrogen cooling system
H. Cease, D. DePoy, G. Derylo, H. T. Diehl, J. Estrada, B. Flaugher, K. Kuk, S. Kuhlmann, A. Lathrop, K. Schultz, R. J. Reinert, R. L. Schmitt, A. Stefanik, A. Zhao
Author Affiliations +
Abstract
The Dark Energy Camera and its cooling system has been shipped to Cerro Tololo Inter-American Observatory in Chile for installation onto the Blanco 4m telescope. Along with the camera, the cooling system has been installed in the Coudé room at the Blanco Telescope. Final installation of the cooling system and operations on the telescope is planned for the middle of 2012. Initial commissioning experiences and cooling system performance is described.
© (2012) COPYRIGHT Society of Photo-Optical Instrumentation Engineers (SPIE). Downloading of the abstract is permitted for personal use only.
H. Cease, D. DePoy, G. Derylo, H. T. Diehl, J. Estrada, B. Flaugher, K. Kuk, S. Kuhlmann, A. Lathrop, K. Schultz, R. J. Reinert, R. L. Schmitt, A. Stefanik, and A. Zhao "Commissioning and initial performance of the Dark Energy Camera liquid nitrogen cooling system", Proc. SPIE 8446, Ground-based and Airborne Instrumentation for Astronomy IV, 84466S (24 September 2012); https://doi.org/10.1117/12.926634
Lens.org Logo
CITATIONS
Cited by 3 scholarly publications.
Advertisement
Advertisement
RIGHTS & PERMISSIONS
Get copyright permission  Get copyright permission on Copyright Marketplace
KEYWORDS
Imaging systems

Cooling systems

Telescopes

Liquids

Cameras

Nitrogen

Charge-coupled devices

RELATED CONTENT

The cryostat for the GRAVITY beam combiner instrument at the...
Proceedings of SPIE (September 12 2012)
The Dark Energy Survey CCD imager design
Proceedings of SPIE (July 09 2008)
Cooling the Dark Energy Camera instrument
Proceedings of SPIE (July 09 2008)
The REMIR cryogenics restyling
Proceedings of SPIE (June 28 2006)
Assembly of the Dark Energy Survey CCD Imager
Proceedings of SPIE (July 26 2010)

Back to Top